EPC – этилен, гелий и не только

EPC – ethylene, helium and beyond

Expertise

In the early 2010s, a client — an independent oil company that had been dynamically developing for over twenty years — conducted laboratory research and discovered ethane in its extracted oil in volumes sufficient for its industrial use in the petrochemical industry. The idea of commercial development of associated gas for the construction of an ethylene and polyethylene production plant was born. By the beginning of 2018, it was decided to organize a tender to select a leading internationally recognized contractor to enter into a contract with the winning participant for engineering, manufacture and supply of production equipment and commissioning work.

Project and Participants

The goal of the project was to build an ethylene production unit with a capacity of over 500,000 tons of ethylene and polyethylene per year. Leading European, US, Chinese and Japanese engineering companies with licensed technology for ethane pyrolysis and production of the finished product on an industrial scale were allowed to participate in the tender.

Participation in the Project and Expertise

Our firm’s participation in the project began in December 2017, during negotiations in Houston, Texas, with the aim of concluding the necessary license agreements for the production of ethylene and polyethylene. The main stage of legal work began in March 2018 with the discussion and consulting of the client in the process of agreeing on conditions of basic design and project financing from each of the foreign tender participants. The summer of 2018 was devoted to preparing the main conditions of an EPC contract, with the involvement of specialized Russian research institutes responsible for preparing and approving working and project documentation. In the early autumn of 2018, our firm helped prepare the documentation that formalized the choice of the tender winner and began designing and coordinating the project documentation with the tender winner. For your understanding, we are talking about hundreds, if not thousands, of pages of documents that detail all aspects of engineering and design work, ordering and delivering equipment manufactured for the designated plant, conducting commissioning work and launching production.

Helium+

An inexperienced reader may ask — what does helium have to do with the project? Plant construction projects are complex and multifaceted. To successfully operate a polyethylene production plant, at least five more plants are required for fractionating ethane from oil, subsequent ethane cracking, and the polymerization process of the corresponding gas fraction to obtain polyethylene. In addition, helium can be present in natural gas extracted alongside oil. It is obtained from associated natural gas by fractional distillation. Each of the described processes requires the construction of a separate plant and obtaining a license. Our firm helped the client throughout 2018 to design and agree on a wide range of documents, including the production of helium and the distribution of liquefied hydrocarbon gas.

Project Completion

The project documentation was successfully approved and signed at the end of 2018 and the beginning of 2019. For example, the signing of documentation for ethylene took 48 hours of continuous work without rest or sleep. This was the first time in the company’s history when the client was surprised to see a bill that indicated the duration of work as 24 hours in a day. Currently, the client company is successfully implementing its project, while our lawyers recall more than nine months of negotiations, sleepless nights, flights to see their families on weekends, and returning to the client’s office early Monday morning to continue negotiations and consulting.

Related articles

See all news
  • 祝你蛇年牛逼!

    祝你蛇年牛逼!Wishing you a prosperous and successful Year of the Snake! May this year bring you good health, steady progress, and meaningful achievements....
    Learn More
    Image of 2025 Chinese New Year of the Snake card
  • Adopting the Zero Trust Model in Corporate Communication

    The Zero Trust model, originally developed as a cybersecurity framework, emphasizes the principle of "never trust, always verify." Initially designed...
    Learn More
    Image for Article on Zero Trust Model in Internal Communications
  • Wishing you happy holidays and a prosperous New Year!

    Thank you for your continued partnership and trust throughout the year. As we look forward to the New Year, may it bring you and your loved ones...
    Learn More
    Happy New Year!
  • Financial Covenants: Creditor Protections Across Agreements

    Financial covenants are a fundamental aspect of creditor-debtor relationships, forming a vital layer of protection for creditors. Whether within the...
    Learn More
    Image for Article ARTICLE - UnderstandingFinancialCovenants
  • Good Faith in English Law: Clarifying the Limits of Contractual Duties in Faulkner v. Vollin

    Good faith is not a general principle implied into contracts under English law unless expressly included. However, where parties do include a...
    Learn More
    Image for Article 'Good Faith in English Law'
  • Resolving Disputes Before Court: A Cost-Saving and Profit-Boosting Strategy

    Just 10–15 years ago, corporate legal departments were typically small, with most legal work outsourced to outside counsel. However, over time,...
    Learn More
    Image for article "Pre-Court Claim Procedure"
  • Key Legal Issues in Project Finance

    Project finance involves the financing of long-term infrastructure, industrial projects, and public services based on a non-recourse or limited...
    Learn More
    Image for Article 'Key Legal Issues in Project Finance'
  • New Draft Law Allows Foreign Bank Branches in Russia

    On July 19, 2024, the Russian government introduced a draft law aiming to permit the establishment of branches of foreign banks in Russia. This law...
    Learn More
    Image for Trend Regarding Branches of Foreign Banks in Russia
  • Essential Factors in Negotiating Generative AI Agreements

    This article highlights the significant distinctions to consider when negotiating the use of generative AI software platforms, compared to...
    Learn More
    Image for the article "Essential Factors In Negotiating Generative AI"
  • The Parol Evidence Rule under English Law

    The parol evidence rule is a fundamental principle in English contract law that serves to preserve the integrity of written agreements by limiting...
    Learn More
    Image for article "Parol Evidence Rule under English law"
  • Understanding Contract Forms in Nuclear Power Plant Projects

    Nuclear power plants represent a significant investment in energy infrastructure, requiring precise coordination of engineering, procurement, and...
    Learn More
    Image for Article "Entering The Nuclear Industry"
  • Key Aspects of Planning Low-Cap/Mid-Cap M&A Deals

    Mergers and Acquisitions (M&A) encompass numerous subtleties that require detailed consideration of the deal planned, its funding procedure, the...
    Learn More
    Image for article "Key Aspects of Planning Low-Cap/Mid-Cap M&A Deals"